Distributed Energy Resource Management System Expansion

62-Distributed-Energy-Resource-Management-System-Expansion-e1687188682225

What we will do and why

Expansion of the existing Distributed Energy Resource Management System (DERMS) platform to cater for a wider variety of network constraints, across a wider proportion of the network, with more dynamic and closer to real-time functionality.

Key deliverables

  • Enhanced software applications including a load flow based constraint management system.
  • Data quality enhancements.
  • Cross-application integration (involving Flex Dispatch platform, Flex Market platform, DERMS).
  • New non-firm Connections products (voltage, fault level) to manage additional electrical problems.
  • Wider roll out of Dynamical Line Rating (DLR) unlocking more capacity.

Target outcomes

  • More intelligent, dynamic and closer to real-time functions/ actions.
  • Increased network headroom and safety.
  • Improved customer journey.
  • Large suite of products we can offer customers for cheaper and faster Connections (voltage, fault level constraints).

Measures of success

  • Accuracy of the operational decisions.
  • Increased in customer satisfaction.
  • Decrease in network curtailment.

Stakeholder Engagement

The DERMS platform is a regular topic of discussion in Distributed Energy Resource forums throughout the year to capture customer views and incorporate it into this project.

Public Detailed Docs

Planned start:

01.04.2023

Target completion:

01.03.2028

Key milestones:

  • Release of enhanced Import functionality (Mar 2024)
  • CIM model populated with necessary data parameters (Mar 2025)
  • Release of Enhanced functionalities (Cancelled)
  • Automate existing processes (Mar 2025)
  • Release of enhanced functionality on fault level (Jun 2025)

Status:

On Track

Date of change Category Description
28.06.2024 Update

Release of Enhanced functionalitie milestone has been split into 2 parts. Part 1 Release of enhanced Import functionality is complete. Part 2 Release of enhanced functionality on fault level due date is set for June 2025 (was March 2025). Team needs more time to accomodate newly found enhancements.

24.12.2023 Update

We added a summary of stakeholder engagement and links to more information. Further milestones are expected to be added later in 2024/25.