What we will do and why

Installer Portals and Back Office systems that allows Installers to apply for multiple Low Carbon Technology Installs (including Electric Vehicle Charging Points, Heat Pumps and Solar Panels and more) for Commercial and Domestic existing premises as well as other 'General Enquiries' services.

Key deliverables

  • Providing a portal for a clear user experience to our installers and customers to capture the information required by UK Power Networks for critical processes such as Low Carbon Technology approvals, Payment Processing and updating the Priority Services Register.

Target outcomes

  • Increased accuracy of data from customer, lack of requirement for back and forth communications from Gateway, SDC and Customer Service.

Measures of success

  • Customer Satisfaction & Increased Time to Connect

Stakeholder Engagement

We have been engaging directly with business teams on their existing processes and exploring methods of automation, along with engagement with internal and external users for testing of the end products. We hold initial design and requirements workshops for each solution, then engage teams throughout and then a final handover session to deliver the product

Planned start:

03.05.2021

Target completion:

31.12.2024

Key milestones:

  • Smart Enquiries (Dec 2024)
  • Smart Connect (Dec 2024)
  • Smart Consents (Jul 2024)

Status:

On track

Date of change Category Description
28.06.2024 Update

This was added to the DSAP in June 2024 as it was identified as a new strategic digital initiative since our last publication of the action plan in December 2023.